NOTE: This is an exact duplication of
the statement as supplied by Mr. Newstrom, cost incurred to date October 9, 1946.
COST INCURRED
TO DATE - OCTOBER 9, 1946
Statement as
Supplied by Mr. Newstrom
|
TOTAL |
LABOR &
MATERIALS |
LABOR
COSTS |
| Patitions |
737.31 |
Including Labor |
301.51 |
| Arch |
30.08 |
" " |
26.00 |
| Sub Floor |
745.63 |
" "
& Shoring |
453.40 |
| Plastering |
390.93 |
" "
& Removing Old Paper |
68.13 |
| Shelving |
154.66 |
"
" |
114.40 |
| Clothes Closets |
100.00 |
"
" |
50.00 |
| Electrical |
300.00 |
Estimated |
|
| Asphalt Tile |
*493.76 |
|
|
|
Totals |
2,942.37 |
|
1,013.44 |
* Cost of Asphalt Tile given
by Mr. Stevenson of Singer Sewing Machine Co.
Source: National Archives and Records Administration, Washington, DC
|